API-200W, 300W, 500W, 1kW-VAWT Installation and Operation Manual
10Instructions on maintenance 1. Appropriate and timely maintenance of the system is directly related to the performance and life cycle of it. Key p
11output 2. Output wire is broken 3. Rectifier is damaged 2. Find out the point and reconnect 3. Change the rectifier Output capacity of the storag
2Instructions for installation, testing and maintenance for 200W-1KW vertical axis wind turbines About the product This product can be used by i
a)Connect the base with the generator,keeping them concentric, screwing tight with hexagon head bolts(M10X25) and spring washers(Φ10), referring
d)Put the keys(6X20) into trough of the axis, connect the nether flange with the main axis from the upper sleeve, and screw tight with screws(M6), r
Drawing 6 g)Connect the blades with the sustaining arms, screw tight with bolts(M5X30), bolts(M5X50), spring washer(Φ5)and locknuts (M5), referrin
h)Wipe silica gel onto the two side section of the blades, connect with the flaps and screw tight with bolts(M6X16), plain washer (Φ6) and spring wash
j)Screw the lifting eye bolt (M8) into the base, and lift the windmill onto the pillar by crane. Make sure the stableness of the windmill in the proce
Drawing 12 Note:All bolt joint points must be coated with thread locking glue. 4 Testing 1. Check all the bolts before the testing to make sure th
Off grid system connecting Drawing 13 On grid system connecting Drawing 14 9